Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2020 | TDOT-EXCAV GENERAL INSPECTION | Approved | Closed, Concrete collars completed. All punch list completed. | |
| 01/17/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Main piping completed. Roadway patches completed. Working on concrete collars at valves. | |
| 10/28/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Called contractor and left message. Called SW GAS and told Tricia about the punchlist items not corrected and that contractor not calling back | |
| 10/24/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | No additional work to repair defficiencie. Will call SW GAS. | |
| 10/10/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Called contractor and SW GAS to find out date that the section of Glenn is to be repaired as per moratorium. | |
| 10/04/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Notified contractor about wadels left at storm drains at Mountain View. Check out complaints from citizen. |
|
| 10/02/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Still working on punch list. Section of concrete curb replaced at Craycroft intersection. Waiting on response to their question on the short section of moratorium before striping patches. | |
| 09/24/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | RAIN. Patching on going. | |
| 09/17/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Patching streets. | |
| 09/09/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Repairing defects in roadway. | |
| 09/04/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Crew working at Swan end on asphalt patches replacing bad work. | |
| 09/04/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Crew replacing temp patches and defective patches. | |
| 09/03/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Crew working on new asphalt patches. Glenn was just striped full roadway. Stripes were placed over temp. patches by city. | |
| 08/29/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Crew replacing bad asphalt patches. | |
| 08/22/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working on repairing roadway at Swan end. | |
| 08/21/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Walked contractor pointing out items that need correction. Pointed out that there is a section of Glenn from Craycroft 1000ft or so that is under moratorium. Start correction action 8/22/19 at Swan end. | |
| 08/19/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Gas pipe completed. | |
| 08/12/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working at Swan end. | |
| 07/23/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Found that NPL started using the old entry to Glenn St. storage yard again and got sidewalk and bike lane covered with gravel and dirt. After jumping contractor they are now placing a man to sweep 8 hours a day till completed with project. | |
| 07/22/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Found that the old entry to storage yard on Glenn was being used and had large amount of dirt and gravel on sidewalk and bike lane. Called contractor and SW GAS to have this cleaned up immediately. Contractor called said all cleaned up. | |
| 07/16/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working on misc. spots along Glenn. Closed west bound lane at Craycroft. | |
| 07/09/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working in Glenn. No detours. Using flagmen. | |
| 06/26/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Barricades at Craycroft end for road closer wrong. Need to install as per approved barricade plans in permit. | |
| 06/11/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Meting at job site. Revised traffic plan at Orlando/Glenn. | |
| 06/06/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working in west bound lane with flagmen. | |
| 05/21/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Sections of trench has roadway repaired. Boring near Magnolia and welding pipe near Magnolia to be pulled under box culvert. Flagmen on site with barricadesl. Traffic flowing. | |
| 05/09/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | At Craycroft end - laying gas pipe, backfilled sections, placed asphalt, barricades and flagmen. | |
| 04/30/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working in street near Craycroft. | |
| 04/23/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Potholing along Glenn with barricades and flagmen. | |
| 04/18/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Warning signs up (2). | |
| 04/16/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pre-con. Reviewed scope of work, use flush traffic plates on Glenn for safety. Contractor thinks may need to modify barricades due to liminated room to work but will proceed and will request meeting in near future with supervisor - told Matt. | |
| 04/12/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pre-con set up for 4/16/19, 9:30 at site. |