Permit: T19RW01201

Parcel: 103082880

Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
05/07/2019 TDOT-EXCAV GENERAL INSPECTION Approved Repairs completed. No issues
05/01/2019 TDOT-EXCAV GENERAL INSPECTION Continued Contractor poured 2 ea. replacement panels on southend that were previously rejected for exceeding ADA crossslope.
04/26/2019 TDOT-EXCAV GENERAL INSPECTION Continued 2 panels replaced on south end exceed ADA crossslope tolerance.
Notify Tito from DR Horton for compliance. Also inform him permit is expired and needs to be renewed
04/25/2019 TDOT-EXCAV GENERAL INSPECTION Continued Contractor removed and repoured last 2 panels on south end.
04/16/2019 TDOT-EXCAV GENERAL INSPECTION Continued Last south side walk panel is cracked. Notify contractor. No issues with ADA compliance
04/10/2019 TDOT-EXCAV GENERAL INSPECTION Continued Concrete pour completed today
04/09/2019 TDOT-EXCAV GENERAL INSPECTION Continued Forms and subgrade inspection approved for pour
04/08/2019 TDOT-EXCAV GENERAL INSPECTION Continued Form inspection failed subgrade densiy requirements