Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: TRSP - ROW - Recurring
| Date |
Description |
Inspector |
Results |
Comments |
| 10/16/2020 |
TRSP - ROW - Recurring |
|
Passed |
TDOT-EXCAV GENERAL INSPECTION - SWF build complete. No further ROW concerns. |
| 09/17/2020 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued - Cores replaced from utility potholes for bore look good. Sidewalk replacement at entrance to car wash from Country Club also approved. Waiting on pole foundation to be poured before backfilling of remainder of power conduit run. |
| 09/04/2020 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued - Pouring Sidewalk panel on Country Club today. Will replace core in roadway next week. |
| 10/16/2020 |
TRSP - ROW - Recurring |
DR |
Approved |
Entered by DROBERT1 - SWF build complete. No further ROW concerns. |
| 09/17/2020 |
TRSP - ROW - Recurring |
DR |
Continued |
Entered by DROBERT1 - Continued - Cores replaced from utility potholes for bore look good. Sidewalk replacement at entrance to car wash from Country Club also approved. Waiting on pole foundation to be poured before backfilling of remainder of power conduit run. |
| 09/04/2020 |
TRSP - ROW - Recurring |
DR |
Continued |
Entered by DROBERT1 - Continued - Pouring Sidewalk panel on Country Club today. Will replace core in roadway next week. |