Inspection Status: Closed
Inspection History: TDOT-Routine Barricade Inspect
| Date |
Description |
Inspector |
Results |
Comments |
| 05/22/2019 |
TDOT-Routine Barricade Inspect |
|
Closed |
SW GAS working in same area as cold patch. Area will be repaired later by SW GAS. |
| 05/08/2019 |
TDOT-Routine Barricade Inspect |
|
Continued |
North lane of Tanque Verde pot hole has cold patch. |
| 04/23/2019 |
TDOT-Routine Barricade Inspect |
|
Continued |
South lane of east bound Tanque Verde is repaired. North lane of West bound Tanque Verde still has a very small cold patch. |
| 04/15/2019 |
TDOT-Routine Barricade Inspect |
|
Continued |
Bore work completed. used cold patch in roadway, 2 places. |
| 04/09/2019 |
TDOT-Routine Barricade Inspect |
|
Continued |
Change of barricade company. Told contractor can not start until the permit is revised to reflect this. Office notified inspector that the change was made to permit. |
| 04/03/2019 |
TDOT-Routine Barricade Inspect |
|
Continued |
Pre-con at 1:15 at site. Will replace width of travel lane east bound in Tanque Verde |
| 03/11/2019 |
TDOT-Routine Barricade Inspect |
|
Not ready for Inspection |
Bluestaked, layout work location, no work. |