| 02/15/2019 | TDOT-EXCAV GENERAL INSPECTION | Approved | Completed. Roadway repaired and barricades removed. Still working on private property. | |
| 02/12/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Roadway still needs pavement, street still closed, permit renewed - confirmed by Lance. Photos sent to Lance. Neighbor complained. Contractor stated that paver is to work on 2/18. |
|
| 02/08/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | They had to wait for Pima County inspection for the sewer tie in. Now that it passed and trench was back filled they are trying to get Tucson Asphalt to pave the road. They are delayed do to rains delaying the paver on their other jobs. Told them they need to renew the permit and that I need the road opened ASAP. They will look for other paver if Tucson Asphalt is not Ble to get the work done. |
|
| 01/23/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Roadway barricaded - closed roadway with detour and protect work area. new pipe in trench waiting on Pima County inspection/test. | |
| 01/14/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pre-con at site, start 1/15/19. Road closure. Perm. asphalt to be used as well as ABC for backfill. | |
| 01/09/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Contractor called will start on septic removal on 1/10 but will call for pre-con before they are to start any work in right of way. |