Inspection History Details
Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/24/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | 1/7/19 area saw cut and precon on site 1/8/19-1/11/19 work performed installing conduit on north side of roadway half at a time. Flaggers were used because of the school located to the East. Sidewalk was removed and will be replaced 1/14/19-1/18/19 work started and complete on the south side of the roadway. all backfill was monitored and area will be restored with new asphalt as soon as possible 1/22/19 sidewalk on North side of Hemisphere restored with no issues and asphalt was repaired across the whole roadway. No issues with project |
|
| 01/24/2019 | TDOT-EXCAV GENERAL INSPECTION | Approved |