Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2020 | PLUMBING - FINAL | Approved | RVI - ALL ELEMENTS WERE INSPECTED BY STATE OFFICE OF MANUFACTURED HOUSING. | |
| 01/09/2020 | PLUMBING - FINAL | Correction Required | Corrections not completed. | |
| 01/07/2020 | PLUMBING - FINAL | Denied | 1- Shall expose the P.O.C. of new bldg sewer to the existing bldg. sewer. 2- Provide tracer wire on bldg sewer. |
|
| 01/03/2020 | PLUMBING - FINAL | Denied | Denied Need gas pressure test | |
| 12/16/2019 | PLUMBING - FINAL | Partial Approval | H2O ok Need water test on new pvc rough. Add gas to permit and do pressure test on all new lines for inspection. Ok to backfill water only. |