Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/05/2022 | FIRE SPKLR - FINAL | Approved | CBASALDUA approved the fire sprinkler final on the GC's permit T18CM06022 on 06/22/2020. | |
| 06/01/2020 | FIRE SPKLR - FINAL | Partial Approval | 1. Ok for Phase 2. 2. Ok for Phase 1 bay area drops. |
|
| 03/23/2020 | FIRE SPKLR - FINAL | Partial Approval | Partial for Phase 1 except for bay area drops. | |
| 02/12/2020 | FIRE SPKLR - FINAL | Partial Approval | Contractor just wanted above ceiling to be inspected before tiles are put in. Count as Sprinkler inspection, if not ready on next inspection fee will be added on CM permit. |