Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 12/05/2019 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Approved |
East side of street all fire lines and risers approved |
| 12/02/2019 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Cancelled |
Cancelled by contractor |
| 11/26/2019 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Partial Approval |
-Fire line on east side of street between buildings 3 & 4 OK to backfill. The entire line on the east side still needs a hydro test. |
| 11/06/2019 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Partial Approval |
Fire line to all buildings on west side of road approved. |
| 10/21/2019 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Meeting |
Stainless steel risers will be installed in each building and tied into the underground prior to hydro testing. |