Inspection Status: Approved
Inspection History: FIRE PUMP - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 11/17/2020 |
FIRE PUMP - FINAL |
|
Approved |
|
| 03/11/2020 |
FIRE PUMP - FINAL |
|
Partial Approval |
Tested the fire pump on temporary power. Pump passed the curve test. Need to verify waterflow with the generator and confirm signals to the FACP once that is installed. Pump is active and we can have water flow from the building. |