Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 11/17/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Approved |
|
| 05/28/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
14th Floor OH/Hydro Piping Test. 223psi. |
| 05/21/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
13th Floor OH/Hydro Piping Test. 217psi. |
| 05/08/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
11th floor partial. OH/Hydro test approved on residential, burn side only. |
| 05/05/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
10th Floor OH/Hydro Piping Test. 220psi. For piping replacement in Fire Damage area only. |
| 04/30/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
9th Floor OH/Hydro Piping Test. 215psi. For piping replacement in Fire Damage area only. |
| 04/22/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
8th Floor OH/Hydro Piping Test. 209psi. For Fire Damage area only. |
| 04/14/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
12th Floor OH/Hydro Piping Test. 227psi. |
| 04/14/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
6th Floor OH/Hydro Piping Test. 210psi. For Piping replacement in Fire Damage area only. |
| 04/06/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
5th Floor OH/Hydro Piping Test. 219psi. For Piping replacement in Fire Damage area only. |
| 03/24/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
4th Floor OH/Hydro Piping Test. 220psi. For Piping replacement in Fire Damage area only. |
| 03/24/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
11th Floor OH/Hydro Piping Test. 205psi. Included all Plastic Pipe. Steel piping will be tested at a later date. |
| 03/16/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
10th Floor OH/Hydro Piping Test. 215psi. Included all Plastic Pipe. Steel piping above previous fire damage will be tested at a later time. |
| 03/06/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
9th floor partial OH/Hydro @ 213 PSI |
| 03/04/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
8th floor OH/Hydro @214 PSI |
| 02/20/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
7th Floor OH/Hydro Piping Test. 215psi. |
| 02/13/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
6th Floor OH/Hydro Piping Test. 205psi. |
| 02/05/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
5th Floor OH/Hydro Piping Test. 225psi. |
| 01/15/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
4th Floor OH/Hydro Piping Test. 200psi. Includes everything except fire damage area that will be replaced and tested separately. |
| 12/19/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
3rd Floor OH/Hydro Piping Test. 210 PSI. |