Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
Permit Number - T19FC00671
Inspection Description - FIRE SPKLR - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/12/2019 | FIRE SPKLR - FINAL | Approved | ||
11/01/2019 | FIRE SPKLR - FINAL | Partial Approval | Okay to dry stock only "pending" all ceiling tiles are in place, caps are removed from heads, and sprinkler heads in the rear are moved away from duct work. If not complete by Monday AM dry stocking shall not be initiated. If stocking begins prior to approval fines shall be added. Re-inspection fee added. |
|
10/29/2019 | FIRE SPKLR - FINAL | Correction Required | Looking to get TCO for stocking. Informed them that the sprinkler system shall be active in order to do so. Kazal is sub doing work. * Informed that one sprinkler head shall be added on main floor on east side of building. * All sprinkler heads shall be installed prior to approval and caps removed. * Insulation shall not be sitting on top of sprinkler heads. Re-inspection fee will be added. |