Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
Permit Number - T19CM09398
Inspection Description - ELECTRIC - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/24/2022 | ELECTRIC - FINAL | Approved | Approved, UPS1 & 2 complete ok to occupy open office 37, 38. | |
03/10/2022 | ELECTRIC - FINAL | Partial Approval | Partial, UPS 1 & 2 installed ok to test and transfer loads. | |
01/27/2022 | ELECTRIC - FINAL | Partial Approval | Partial, awaiting installation of UPS. | |
01/06/2022 | ELECTRIC - FINAL | Partial Approval | Partial, pending PDU installation and Inspection. | |
10/12/2021 | ELECTRIC - FINAL | Partial Approval | Partial, Administrative offices and conference room ok for TCO. |