Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Interior Shear Bracing
Permit Number - T19CM09164
Inspection Description - COT - HCBU - Interior Shear Bracing
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2022 | COT - HCBU - Interior Shear Bracing | WGALLAGHER | Approved | Entered by NGARCIA3 - Approved |
| 11/30/2021 | COT - HCBU - Interior Shear Bracing | TGAUSP | Partial Approval | Entered by RSALDAT1 - Approved for all 2nd floor units |
| 11/19/2021 | COT - HCBU - Interior Shear Bracing | ESTEVENS | Partial Approval | Entered by VVERA1 - Partial. Room 209, 207, 205, 203, 201. |
| 11/15/2021 | COT - HCBU - Interior Shear Bracing | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Apartment units #211 and 213. Ok to tape throughout. |
| 11/05/2021 | COT - HCBU - Interior Shear Bracing | ESTEVENS | Partial Approval | Entered by RSALDAT1 - Partial. Unit 210, 206, 204, 202. |
| 11/03/2021 | COT - HCBU - Interior Shear Bracing | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Level #2; Units 212, 214, 216. Ok to tape progress areas. |
| 08/25/2021 | COT - HCBU - Interior Shear Bracing | RELEFANTE | Partial Approval | Entered by NGARCIA3 - PA Units 201 202 206 208 210 212 214 216 |
| 08/18/2021 | COT - HCBU - Interior Shear Bracing | RELEFANTE | Partial Approval | Entered by RSALDAT1 - PA above ceiling only Units 204 203 205 207 209 211 213 215 |
| 07/16/2021 | COT - HCBU - Interior Shear Bracing | RELEFANTE | Partial Approval | Entered by RSALDAT1 - PA Inspected only 1 side of each dimizing wall, contractor still needs to fire caulk all penetrations and need to put puddy pads on electrical boxes |
| 06/25/2021 | COT - HCBU - Interior Shear Bracing | JBURGE | Partial Approval | Entered by VLEON1 - Partial. Level #2 Corridor; Ok to tape progress areas. |