Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
Permit Number - T19CM08816
Inspection Description - COT - LCBU - Excavation/Rebar/Zoning
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/17/2021 | COT - LCBU - Excavation/Rebar/Zoning | KCOCO | Approved | Entered by VLEON1 - APPROVED |
01/22/2021 | COT - LCBU - Excavation/Rebar/Zoning | DQUINN | Approved | Entered by VLEON1 - APPROVED |
12/18/2020 | COT - LCBU - Excavation/Rebar/Zoning | ESTEVENS | Partial Approval | Entered by RSALDAT1 - Partial. Second pad on the south side. |
12/15/2020 | COT - LCBU - Excavation/Rebar/Zoning | DQUINN | Partial Approval | Entered by VLEON1 - N. S pads on west side ok to pour |
09/30/2020 | COT - LCBU - Excavation/Rebar/Zoning | DMUNIZ | Partial Approval | Entered by RSALDAT1 - Partial, Contactor slab ok for concrete placement. |
08/31/2020 | COT - LCBU - Excavation/Rebar/Zoning | DMUNIZ | Partial Approval | Entered by JSCHNEI2 - Partial, Footings for Remediation well @ new booster station ok for concrete placement. |
08/28/2020 | COT - LCBU - Excavation/Rebar/Zoning | DMUNIZ | Partial Approval | Entered by RSALDAT1 - Partial, Duct bank installation from Existing Electrical Vault to New PLC & Power panel, and continued to location of new Communication & Electrical Vault. |