Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/05/2019 | PLUMBING - INTERMEDIATE | Approved | ||
| 10/28/2019 | PLUMBING - INTERMEDIATE | Partial Approval | Okay Inside home only. Main water supply needs to be a minimum 12" deep in ground. Secure pluming risers. Leave trench open for inspection. | |
| 10/24/2019 | PLUMBING - INTERMEDIATE | Denied | 1. Install blue tracer wire on all new underground pvc. 2. Run copper to below grade at all pvc risers. 3. Hot joint leak at bathtub. 4. Coat foam insulation outside of kitchen sink to prevent us deterioration. 5. Install drip leg on gas line. 6. Install pan under water heater and tpr drain to within 6”. 7. Screw single wall vent pipe to double wall. |