Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 09/29/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
Both are approved. |
| 09/01/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
Not ready, not complete. |
| 08/27/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Cancelled |
Canceled by contractor. |
| 08/24/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Site wall, where it ended on the south wall to the south east corner, then going to the north east corner and then approximately halfway down the north side wall |
| 08/21/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial. Footings for both stairwells. |
| 08/18/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial approval for site wall pre grout half way on south wall and west wall to entrance, both from southwest corner |
| 08/13/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial. Site wall, North, East and West sides. |
| 08/11/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |