Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/13/2021 |
MECHANICAL - FINAL |
|
Approved |
REVIEW OF AIR BALANCE REPORT COMPLETED |
| 04/14/2021 |
MECHANICAL - FINAL |
|
Partial Approval |
REVIEW OF AIR BALANCE REPORT FOR FIRST FLOOR COMPLETE. SECOND FLOOR REPORT SHOWS EF 2-1 NEEDS TO INCREASE AIR FLOW RATE |
| 04/06/2021 |
MECHANICAL - FINAL |
|
Partial Approval |
PARTIAL LEVEL 2 COMPLETE |
| 10/23/2020 |
MECHANICAL - FINAL |
|
Partial Approval |
Partial. Level #1 complete |
| 10/08/2019 |
MECHANICAL - FINAL |
|
Prior to Final Inspectn |
AIR BALANCE REPORT REQUIRED |