Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/28/2020 | ELECTRIC - INTERMEDIATE | Approved | ||
| 12/18/2019 | ELECTRIC - INTERMEDIATE | Partial Approval | Easy access floor in auditorium ok to close | |
| 12/04/2019 | ELECTRIC - INTERMEDIATE | Partial Approval | ALL LOW VOLTAGE CONDUIT IN AUDITORIUM OK TO COVER | |
| 11/19/2019 | ELECTRIC - INTERMEDIATE | Partial Approval | This inspection was for underground electric as noted on shut EP102.. Ok to proceed |
|
| 11/08/2019 | ELECTRIC - INTERMEDIATE | Partial Approval | 1- Electric panel South of the Switch Gear is okay to energize. | |
| 11/01/2019 | ELECTRIC - INTERMEDIATE | Partial Approval | 1- New service panel and conduit to the switch gear is okay as noted on plan. | |
| 10/23/2019 | ELECTRIC - INTERMEDIATE | Partial Approval | 1- MC cables and metal boxes are okay to cover in Training Room. |