Inspection Status: Approved
Inspection History: ELECTRIC - RECONNECT
| Date |
Description |
Inspector |
Results |
Comments |
| 12/28/2019 |
ELECTRIC - RECONNECT |
|
Approved |
Inspection for Interconnection of New 750KW 480/277V Generator to Existing 1200 AMP SES. TEP Parallel Line sets of 4-#350MCM Conductors RE-directed to new 1200 AMP Automatic TransferSwitch with Shunt trip Capability. System Grounded and bonded per plan. All work meets NEC and local jurisdiction requirements. Verbal Clearance sent to TEP for RECN/INCR @10:20AM. Check of $165 received upon arrival for after hours inspection. |