Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2020 | FIRE - FINAL | Approved | ||
| 01/30/2020 | FIRE - FINAL | Denied | Gate needs to have KNOX switch installed and tested along with the power operation of the gate | |
| 12/09/2019 | FIRE - FINAL | Denied | 1. Need sprinkler monitoring permit. 2. Still need locking FDC cap. |
|
| 11/07/2019 | FIRE - FINAL | Denied | GM not on site. Coordinate with sub contractor to test monitoring system. Shall have a knox box added and locking FDC cap on building. Also no plans were submitted for the monitoring, with that a fee for work without permit will be added if proof can not be given. Re-inspection fee added. |