Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 06/09/2020 |
ELECTRIC - INTERMEDIATE |
|
Approved |
|
| 05/08/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Partial approval all hard deck ceiling areas above restrooms, riser rooms, and Elevator service rooms 1st and 2nd floors |
| 05/07/2020 |
ELECTRIC - INTERMEDIATE |
|
Not ready for Inspection |
Not ready |
| 04/17/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
RVI First floor of building six. OK to one side drywall where roof drains and plumbing will be. OK to drywall exterior walls. |
| 02/21/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Secondaries from switchgear south approximately 70 feet OK. |
| 02/14/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Light cage is OK. |