Permit: T19CM05174

Parcel: 117050340


Addresses:

316 E 6TH ST


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T19CM05174

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
08/20/2021 EXCAVATION/LAYOUT REBAR & ZON Approved AP
02/27/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/25/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns 6.9 to grid line 4. Gridline L.9 to L Footing gridline 6.9 from K.7 to J.7.
02/21/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5 columns ready to pour - 1 at southwest and 4 at southeast corner.
#5 concrete walls ok to pour at ne elevator.
02/19/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/18/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North wall gl 4 - 1 on D.1 ok to pour
02/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns at : 7 A-J, I-9, I - 2-3, H - 2-3, H -2. Ok to pour
02/11/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/10/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/08/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTINGS AND COLUMNS (INSP FROM 12PM-2P)
02/07/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
02/06/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval East side footings - north 2/3 - ok to pour

West shearwall ok to pour

Remainder of west and middle columns ok to pour
01/30/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WF2 FOOTING ALONG NORTH WALL GL E - W, AND F10 FOOTINGS FROM E.2 - D AND 3 - 5