Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2019 | PLUMBING - GAS PRESSURE TEST | Approved | Needs PDSD SW Gas Clearance, Reconnect SW Gas Was Called for Clearance, Reconnect, June. Done |
|
| 07/17/2019 | PLUMBING - GAS PRESSURE TEST | Denied | 1- Shall provide a Mechanical Engineer to assess the existing gas system and provide direction on how to eliminate water residue that was introduced to the gas system due to the plumbing contractor connecting the gas system to the domestic water distribution. 2- Shall submit the Engineers written response with direction to the Building Official for approval. |