Inspection Status: Passed
Inspection History: COT - HCME - Mechanical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 12/08/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Approved |
Entered by RSALDAT1 - Approved. |
| 11/22/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - . Partial. Level 1. Area A. Complete except for corridor 1037, 1036.
|
| 10/11/2021 |
COT - HCME - Mechanical Intermediate |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Supply and return lines for chilled water system on Level #1 and stubbed up to Level #2. Ok to insulate and cover progress areas. Level #2, East area: duct work system is insulated. |
| 08/19/2021 |
COT - HCME - Mechanical Intermediate |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - . Partial. Level #1, duct systems in Area B and Area C. Ok to insulate duct systems. |
| 08/13/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Level 2. Area C. Hard duct only. |
| 08/02/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Partial Approval |
Entered by RSALDAT1 - 4035, 4036. Partial. Area A and C on level 1 and Area C on level 2. See contractors plan for areas inspected. |
| 07/16/2021 |
COT - HCME - Mechanical Intermediate |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Hydronic lines (hot water) at 3”-8” in Area C. Ok to insulate progress areas. |
| 07/06/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Partial Approval |
Entered by RSALDAT1 - Partial. RTU number eight supply and return duct |
| 06/17/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Partial Approval |
Entered by VLEON1 - Partial. RTU duct and fire dampers for RTU 7&8. |
| 05/06/2021 |
COT - HCME - Mechanical Intermediate |
ESTEVENS |
Partial Approval |
Entered by VLEON1 - Area A. See contractors plans for highlighted areas inspected.
|