Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/28/2021 | MECHANICAL - FINAL | Approved | Approved. Awaiting results of air balance testing. Results to be forwarded to R. Sherry. | |
| 07/20/2021 | MECHANICAL - FINAL | Partial Approval | PARTIAL NEED AIR BALANCE TEST RESULTS FORWARDED TO R. SHERRY | |
| 07/16/2021 | MECHANICAL - FINAL | Partial Approval | Partial. Level #1, Lobby area, main entry area, lounging area. | |
| 07/14/2021 | MECHANICAL - FINAL | Partial Approval | Partial. Level #; Room Units 301-347; Electric Room and storage rooms. Level #2; Room Units 201-248; Electric Room, storage areas, and conference rooms. |
|
| 07/13/2021 | MECHANICAL - FINAL | Partial Approval | Partial. Level#5: Room Units 501-548: Electric Room and storage rooms. Level #4: Room Units 401-448: Electric Room and storage rooms. | |
| 07/12/2021 | MECHANICAL - FINAL | Partial Approval | Partial. Level #6; Room Units 601-646 | |
| 07/09/2021 | MECHANICAL - FINAL | Not ready for Inspection | Not ready. Contractor cancelled. |