Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 06/13/2022 |
BUILDING - FINAL |
|
Approved |
|
| 08/24/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Need Fire Finals. |
| 08/23/2021 |
BUILDING - FINAL |
|
Partial Approval |
Partial. Need Fire Finals |
| 08/20/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Need Fire Finals and Right of way final. |
| 08/16/2021 |
BUILDING - FINAL |
|
Partial Approval |
REVIEW OF AIR BALANCE REPORT COMPLETED |
| 07/29/2021 |
BUILDING - FINAL |
|
Partial Approval |
Partial. Building met standards to make,application for a Temporary Certificate of Occupancy. |
| 07/28/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Information only (TCO). |
| 07/27/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED |
| 07/26/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
. Not ready. Information only for TCO requirements. |
| 07/22/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Information for pre-C of O requirements. |
| 07/09/2021 |
BUILDING - FINAL |
|
Partial Approval |
Partial. Information only: process for obtaining a Certificate of Occupancy. |