Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2021 | FRAMING | Approved | ||
| 03/08/2021 | FRAMING | Partial Approval | Partial. Exterior lobby entry area ceiling. | |
| 02/24/2021 | FRAMING | Partial Approval | Partial. Level #1; Lobby areas; restrooms and offices. | |
| 02/22/2021 | FRAMING | Not ready for Inspection | NOT READY CONTRACTOR CANCELLED WILL RESCHEDULE FOR 23 FEBRUARY | |
| 02/18/2021 | FRAMING | Cancelled | ca Per Ricky |
|
| 02/09/2021 | FRAMING | Partial Approval | Partial. Level #2; Room Units 211; 212; 213; 214; 215; 217; 218; 219; 220; 221; 222; 223; 224; 225; 226; 227; 228. Ok to insulate and cover walls. | |
| 01/26/2021 | FRAMING | Partial Approval | Partial. Level #2; Room Units 201 - 208. Ok to insulate and cover walls. Level #2; North. Corridor; Ok to insulate and one side sheet rock. | |
| 01/25/2021 | FRAMING | Cancelled | CANCELLED PER RICKY | |
| 11/24/2020 | FRAMING | Not ready for Inspection | Not ready. | |
| 11/18/2020 | FRAMING | Partial Approval | Partial. Level #6; Section A. Framing for corridor lighting. Ok to cover progress areas. | |
| 11/10/2020 | FRAMING | Partial Approval | Partial. Level #5; Room Units 524-543: entry area and restrooms. Ok to sheet rock progress areas. Area C. | |
| 11/06/2020 | FRAMING | Partial Approval | Partial. Level #5; Unit Rooms entry ceilings and bathroom ceilings; 501-523; 544-548. | |
| 10/29/2020 | FRAMING | Not ready for Inspection | Not ready. Contractor cancelled; will reschedule for 30 October. | |
| 10/28/2020 | FRAMING | Partial Approval | Partial. Level #4; Room Units #414-448. Ok to insulate and sheet rock progress areas. | |
| 10/27/2020 | FRAMING | Partial Approval | Partial. Level #4 Room Units #401-413. Ok to cover walls and ceilings.Level #5; Room Units 518-528; 542-548. Ok to cover walls and ceilings. | |
| 10/26/2020 | FRAMING | Not ready for Inspection | Not ready. Inspection will be rescheduled for 27 October. | |
| 10/21/2020 | FRAMING | Partial Approval | Partial. Level #5; Section C; Room Units 526-542. Ok to insulate and cover walls. | |
| 10/20/2020 | FRAMING | Not ready for Inspection | Not ready. Contractor cancelled. Will reschedule for 21 October | |
| 10/15/2020 | FRAMING | Partial Approval | Partial. Levels #5 & 6 Vending rooms; Laundry storage rooms; Laundry chute rooms. Ok to insulate and sheet rock progress areas. | |
| 10/14/2020 | FRAMING | Partial Approval | Partial. Unable to perform inspection due to time constraints. Will perform inspection on 15 October. Notified site superintendent. | |
| 10/12/2020 | FRAMING | Partial Approval | Partial. Level #6A, Room Units 602; 603; 605; 606; 608; 609; 610; 611; 612; 613; 614; 615; 616; 617: entry area ceilings and bathroom ceilings. Ok to sheet rock progress areas. | |
| 10/07/2020 | FRAMING | Partial Approval | Partial. Level #6; Section C Room Units 626-741. Level #5; Section C Room Units 501-513. Ok to insulate and cover the walls. Drop to add an attachment Attachments |
|
| 10/05/2020 | FRAMING | Not ready for Inspection | contractor will reschedule for 7 October | |
| 09/23/2020 | FRAMING | Partial Approval | Partial. Level #3; Stack A; Room Units #301-317. Level #4; Stack A; Room Units #401-417. Ok to cover walls and ceilings. | |
| 09/21/2020 | FRAMING | Partial Approval | 01035. Partial. Level #6A; Unit Rooms 601-617. Level #6B Unit Rooms 618; 619; 620; 621; 622; 623; 624; 625; 642; 645; 647; 648; 6440. | |
| 09/14/2020 | FRAMING | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 08/28/2020 | FRAMING | Partial Approval | Partial. Stairwells #1 and #2. Ok to insulate and cover walls. Levels #1 through #6. | |
| 08/26/2020 | FRAMING | Partial Approval | Partial. Level #6 Corridor Shear Walls. Ok to cover progress areas. | |
| 07/30/2020 | FRAMING | Partial Approval | partial 1- Shear wall panels and above ceiling for 5th floor Corridor is okay to sheet rock. | |
| 07/29/2020 | FRAMING | Partial Approval | partial 1- This inspection is for the 5th floor pre rock inspection for 24” of the Corridor wall and 8 feet of the Demising walls only. Okay to sheet rock these areas. |
|
| 07/27/2020 | FRAMING | Partial Approval | Partial. Exterior shear walls; East and North. Ok to cover progress areas with waterproof sheathing. | |
| 07/15/2020 | FRAMING | Partial Approval | Partial. Level #4 Corridor ceilings, Ok to insulate and sheet rock and to pre-rock up tp 18” below deck above. | |
| 07/09/2020 | FRAMING | Partial Approval | Partial. Model rooms #310 and 339. Ok to insulate and sheet rock progress areas. | |
| 06/29/2020 | FRAMING | Partial Approval | Partial. Level #3; model rooms #339 and 310. Ok to insulate and cover walls. | |
| 06/29/2020 | FRAMING | Partial Approval | Partial. Level #3; model rooms #339 and 310. Ok to insulate and cover walls. | |
| 06/25/2020 | FRAMING | Partial Approval | Partial. Level #6; South Corridor area, interior shear walls. Bathroom shear walls at #301; 302-303; 317-318; 319-320; 329-330; 332-333. Corridor ceilings. Ok to sheet rock progress areas. | |
| 06/23/2020 | FRAMING | Partial Approval | Partial. Information for stairwell framing. | |
| 06/22/2020 | FRAMING | Partial Approval | Partial. East exterior wall; clips and bracing in place. Ok to insulate progress areas. | |
| 06/16/2020 | FRAMING | Not ready for Inspection | Not ready. Contractor cancelled, East exterior wall, clips not on place. | |
| 05/27/2020 | FRAMING | Partial Approval | Partial. Level #2; Guest rooms and corridor. |