Inspection History Details
Inspection Status: Approved
Inspection History: STEM WALL/RETAINING WALL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2021 | STEM WALL/RETAINING WALL | Approved | ||
| 04/06/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level two, Elevator walls. | |
| 04/02/2020 | STEM WALL/RETAINING WALL | Cancelled | CA per phone call with customer. | |
| 04/01/2020 | STEM WALL/RETAINING WALL | Cancelled | CA per phone call with customer. | |
| 03/31/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level two, Stairwells one and three. Builder will submit field inspection reports from SI. | |
| 03/26/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level 2, D8-17. Column E17. | |
| 03/12/2020 | STEM WALL/RETAINING WALL | Partial Approval | Shear wall from F to G, GL 14. | |
| 03/10/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level two-Columns. G3 at 16, G4, G6, G14, G12, F4, F6, F14, F12, E14, E12, E8, E6, E4, E1, Shear wall 1. | |
| 03/05/2020 | STEM WALL/RETAINING WALL | Partial Approval | Columns Line 8, F, G, H. Line K 1, 3, 6, 8, and 12. | |
| 03/04/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level 1.5. Southwest stair, Columns H14, H17, J14, J17. | |
| 03/03/2020 | STEM WALL/RETAINING WALL | Partial Approval | Shear wall South side, level 1.5, Columns H1, H3, H6, J1,3,6, 8, 12, 14, L1,L3. | |
| 03/02/2020 | STEM WALL/RETAINING WALL | Not ready for Inspection | Work incomplete. | |
| 02/25/2020 | STEM WALL/RETAINING WALL | Partial Approval | Columns. Level 1.5, GLs , 1E, 2E, 6E, 8E, 2F, 6F, 6G, 5G, wall line D from 2-8. | |
| 02/20/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level one, stairwell three. | |
| 02/03/2020 | STEM WALL/RETAINING WALL | Partial Approval | Stairwell two and elevator to level two. | |
| 01/31/2020 | STEM WALL/RETAINING WALL | Partial Approval | Stair one, level two. Grigline D, from grid lines 8-12. Stair two, ground level. Shear wall at grid line L, from grid lines 6-12. | |
| 01/28/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level one, stair one. | |
| 01/28/2020 | STEM WALL/RETAINING WALL | Partial Approval | Level one, elevator shaft. | |
| 01/17/2020 | STEM WALL/RETAINING WALL | Partial Approval | Street level stair 2. | |
| 01/10/2020 | STEM WALL/RETAINING WALL | Partial Approval | GL-D, from GL8-17. | |
| 01/08/2020 | STEM WALL/RETAINING WALL | Partial Approval | Stairwell three level one. | |
| 01/07/2020 | STEM WALL/RETAINING WALL | Partial Approval | Stem wall line D level 1. Columns at GLs B13, C13, C16, and E10 level 1. | |
| 01/02/2020 | STEM WALL/RETAINING WALL | Not ready for Inspection | Builder wanted footing inspection. | |
| 12/31/2019 | STEM WALL/RETAINING WALL | Cancelled | per phone call with customer. | |
| 12/24/2019 | STEM WALL/RETAINING WALL | Not ready for Inspection | Contractor cancelled, rained out. | |
| 12/23/2019 | STEM WALL/RETAINING WALL | Cancelled | CA per phone call with customer. | |
| 12/20/2019 | STEM WALL/RETAINING WALL | Partial Approval | Grid lines D 1-7. Columns at GLs A1, A2, A7, B1, B5, C5, E17, F12, H14, H17, J17, K14. | |
| 12/17/2019 | STEM WALL/RETAINING WALL | Cancelled | on-site by contractor. | |
| 12/16/2019 | STEM WALL/RETAINING WALL | Not ready for Inspection | Contractor cancelled. Will reschedule for 17 December. | |
| 12/13/2019 | STEM WALL/RETAINING WALL | Partial Approval | Stem/retaining wall at GL: 1/F-G; concrete columns at GL: H/1; G/6; F/6. Ok to place concrete in progress areas. | |
| 12/11/2019 | STEM WALL/RETAINING WALL | Partial Approval | 2 columns F14 G14 W3 wall L14/F-G F16 footing line D 1-17 per RFI 16. Ok to proceed |
|
| 12/09/2019 | STEM WALL/RETAINING WALL | Cancelled | Rain out, will reschedule for tomorrow. | |
| 12/06/2019 | STEM WALL/RETAINING WALL | Partial Approval | Columns E8,E6,G8,H8,J8,H6,G6,H3,G3,G12,H12,J12,J14 Ok to proceed |
|
| 12/05/2019 | STEM WALL/RETAINING WALL | Partial Approval | F25 footing Grid line G.3-H/14-17 Columns J3,J6,K3,K6,K12,G3,E3,F3. Ok to proceed |
|
| 12/04/2019 | STEM WALL/RETAINING WALL | Partial Approval | F25 grid line 14-17/J F12 14-17/J.5-L Ok to proceed. |
|
| 12/03/2019 | STEM WALL/RETAINING WALL | Partial Approval | Grid line 17-F 17-F.5 K.5-L/5-13 1-K 3-K 1-L 3-L Ok to proceed |
|
| 12/02/2019 | STEM WALL/RETAINING WALL | Cancelled | Canceled by Mike will recall for tomorrow. | |
| 11/29/2019 | STEM WALL/RETAINING WALL | Cancelled | Will recall for Monday. | |
| 11/27/2019 | STEM WALL/RETAINING WALL | Partial Approval | 7 footings: J1 J2 J6 J7 J12 K6 K12 Ok to proceed |
|
| 11/25/2019 | STEM WALL/RETAINING WALL | Partial Approval | Footing F8,F12,G6,G8,G12,H16 Ok to proceed |
|
| 11/21/2019 | STEM WALL/RETAINING WALL | Cancelled | Canceled by Mike due to rain, reschedule for tomorrow. | |
| 11/20/2019 | STEM WALL/RETAINING WALL | Partial Approval | Footing F18 grid line 14-16, E.5-G.5. Columns CC4, E1,E3,E6,F3,F6,G2 Ok to pour. |