Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T19CM04556
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/07/2020 | BUILDING - PROGRESS | Approved | approved | |
03/03/2020 | BUILDING - PROGRESS | Partial Approval | Mezzanine ok to pour, East end | |
02/14/2020 | BUILDING - PROGRESS | Not ready for Inspection | 1- Work is incomplete | |
02/13/2020 | BUILDING - PROGRESS | Partial Approval | Pre-Grout for elevator shaft to 30’. | |
02/12/2020 | BUILDING - PROGRESS | Partial Approval | 1- Steel reinforcement for the 7th lift of masonry wall is okay for grout for the elevator shaft | |
02/11/2020 | BUILDING - PROGRESS | Not ready for Inspection | ||
02/10/2020 | BUILDING - PROGRESS | Partial Approval | 1- Steel reinforcement is okay for grout for the six lift masonry elevator shaft. | |
02/06/2020 | BUILDING - PROGRESS | Partial Approval | 1- The six lift for the elevator shaft masonry wall is okay for grout. | |
02/04/2020 | BUILDING - PROGRESS | Partial Approval | 1- Elevator shaft masonry fourth lift is okay to grout. 2- Underground electric conduits at North side of bldg. is okay to cover. |
|
02/03/2020 | BUILDING - PROGRESS | Partial Approval | 1- The third masonry lift os okay for grout at elevator shaft. | |
01/28/2020 | BUILDING - PROGRESS | Partial Approval | first lift for elevators, trash enclosure and south wall for mechanical condensers | |
12/26/2019 | BUILDING - PROGRESS | Partial Approval | 1- Second Floor decking has been screwed down as per engineer revised application. Shall provide a revised and approved drawing, proceed at own risk. |