Permit: T19CM04556

Parcel: 132130750


Addresses:

3300 S PARK AV


Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Permit Number - T19CM04556

Inspection Description - BUILDING - PROGRESS

Inspection Status - Approved

Date Description Inspector Results Comments
08/07/2020 BUILDING - PROGRESS Approved approved
03/03/2020 BUILDING - PROGRESS Partial Approval Mezzanine ok to pour, East end
02/14/2020 BUILDING - PROGRESS Not ready for Inspection 1- Work is incomplete
02/13/2020 BUILDING - PROGRESS Partial Approval Pre-Grout for elevator shaft to 30’.
02/12/2020 BUILDING - PROGRESS Partial Approval 1- Steel reinforcement for the 7th lift of masonry wall is okay for grout for the elevator shaft
02/11/2020 BUILDING - PROGRESS Not ready for Inspection
02/10/2020 BUILDING - PROGRESS Partial Approval 1- Steel reinforcement is okay for grout for the six lift masonry elevator shaft.
02/06/2020 BUILDING - PROGRESS Partial Approval 1- The six lift for the elevator shaft masonry wall is okay for grout.
02/04/2020 BUILDING - PROGRESS Partial Approval 1- Elevator shaft masonry fourth lift is okay to grout.
2- Underground electric conduits at North side of bldg. is okay to cover.
02/03/2020 BUILDING - PROGRESS Partial Approval 1- The third masonry lift os okay for grout at elevator shaft.
01/28/2020 BUILDING - PROGRESS Partial Approval first lift for elevators, trash enclosure and south wall for mechanical condensers
12/26/2019 BUILDING - PROGRESS Partial Approval 1- Second Floor decking has been screwed down as per engineer revised application. Shall provide a revised and approved drawing, proceed at own risk.