Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T19CM04364
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/09/2019 | PLUMBING - ROUGH, SOIL | Approved | ||
09/05/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | 1- DWV water test provided. 2- This inspection is for the underground rough plumbing at North West side of bldg. as noted on piping the approved plans. |
|
09/03/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | Gridline 3.17. Meat prep area. | |
08/30/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | 1- DWV water test provided. This inspection is for the underground rough plumbing between grid lines 3.17 to 3.19 and between grid line 3.23 and 3.24 only. |
|
08/29/2019 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | no new work ready for today | |
08/26/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | 1- Sanitary and Grease waste rough plumbing is okay between grid line 3.19 to East demising wall and between 3.20 to 3.23.5 only. Okay to backfill trenches. | |
08/22/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | restroom and break room area ok | |
08/16/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | Main sanitary and grease OK within footprint of building. During this inspection the exhaust was way too high inside the building due to a tamper running all day. No super on site, I expressed my concern to the plumbing foreman that the building needs to be aired out or work needs to stop for a while. | |
08/15/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | 4" grease and sanitary ok from gridline 3.17 to 3.19. Combination waste an vent ok from gridlines 3.17 to 3.18 or east side of sales floor. See highlighted drawing in jobsite trailer | |
08/12/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | Grease waste and Sanitary waste on west end ok to backfill at Restrooms, Cocina , and Tortilleria. Combination waste and Vent system for freezer floor drains mid-west ok to backfill. |