Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/13/2019 |
BUILDING - FINAL |
|
Approved |
condensate piping needs to be painted for UV protection and needs to be up on either Redwood or pressure-treated blocks so it’s not sitting directly on the roof. Service receptacle required when installing a new AC service on the roof. Either add a disconnect that water heater or add lockout tag out breaker at the panel. |
| 06/12/2019 |
BUILDING - FINAL |
|
Not ready for Inspection |