Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2019 | PLUMBING - ROUGH, SOIL | Approved | ||
| 07/05/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | 2 " line from Y fitting cut and capped back to y fitting. | |
| 07/03/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | Building sewer, except for y and dead end piping; plumber will cut and cap. Also need to see repaired washer line with tracer. | |
| 07/02/2019 | PLUMBING - ROUGH, SOIL | Correction Required | 1-Provide bell hole for inspection at all joints to allow for 360 degree inspection. 2-No test on DWV piping. 3-2" line that connects to building sewer needs to be terminated in an accessible manner per IRC section P3005.1.6. Note: Damaged laundry line has been reconnected in another location, however has not been tested. |
|
| 06/27/2019 | PLUMBING - ROUGH, SOIL | Correction Required | Note: Partial inspection of guest house sewer; tie for washing machine is not connected at this time. Provide bell hole for inspection at all joints to allow for 360 degree inspection. |
|
| 06/03/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | OK within building footprint. |