Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date |
Description |
Inspector |
Results |
Comments |
| 10/30/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Approved |
HCS connection to site Sewer For Building 5 & 6 ok to backfill. |
| 10/15/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
Bldg #1, #2, #3 HCS stub from Sewer to buildings ok. |
| 10/11/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
Sewer line from existing manhole south to manhole (still need to put in base for manhole. Need test still. |
| 10/10/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
|
| 10/08/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
Private sewer and HCS connections approximately 10 feet diagonal between manhole one and existing south manhole OK to backfill still need test. |
| 10/07/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
Provide minimum 45° angle at branch taps |