Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 05/13/2020 |
PLUMBING - INTERMEDIATE |
|
Approved |
|
| 09/26/2019 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
Called Gene site superintendent, he is in Mexico. He stated he would call the tile guy to come show me what was to be inspected. The tile guy left at 1 pm and was not returning to site today. Called Matt and left a message stating to recall inspection since no one on site had keys our knew what it was I was to inspect or look at, asked to leave message when it was called next time. |
| 08/26/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Bldg B, shower pans west side second floor |
| 08/21/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
1- Shower base water test provided for the 2nd floor East bldg. B only. |
| 08/01/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
1- Shower base water test provided west bldg. west side of bldg.only. |
| 06/25/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Except shower pans |
| 06/21/2019 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
Work not complete enough to inspect |