Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 06/20/2019 |
ELECTRIC - UNDERGROUND |
|
Approved |
Phase 1 to Phase 2 of Project, Completion of Electrical Underground Conduits Approved and ok to tape encase and backfill. |
| 06/19/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
From canopies F to G and G to H, and from transformer to pull box ok |
| 06/13/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
From south side of main entry road to 15’ north of Grid E and between Gird E to F, both runs ok to pour and backfill |
| 06/07/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
From transformer to junction box and from sidewalk next to road to gear box, both ok to pour and backfill |
| 05/28/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
4-3 1/2” Conduits, 2- 1” Conduits, (100’) from last inspection. East of Canopy D from Existing sidewalk, to under street and beyond. Ok to encase and backfill. Also 3-4" Conduits, 2-1" Conduits (100’) from South of Canopy A to phase 2 of project ok to encase and backfill to road. |
| 05/21/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
4-3 1/2" PVC Conduits, & 2- 1" PVC Conduits from Canopy D to first Sidewalk East of Canopy 200’ ok to encase and backfill. |
| 05/17/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Canopy A to phase 2 and canopy C to D ok to backfill dirt over concrete ,dye and tape |
| 05/16/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Phase 1 underground conduit from Grid A to C on north side of canopies. |