Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - ABOVE CEILING
Permit Number - T19CM01873
Inspection Description - ELECTRIC - ABOVE CEILING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/23/2019 | ELECTRIC - ABOVE CEILING | Approved | ||
08/20/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | rooms 115, 116, 117, 118, 119, 120, 121, 122, 123, 124, hallway 125, storage 132, hallway 181, break room 105, in phase 6 ok. | |
08/14/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | Rooms: 104, 108, 109, and 156 | |
08/09/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | 1- Above ceiling is okay to cover in rooms 101, 102, 110, 111, 112, 113 & 114 only. | |
07/17/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | Phase 6: Rm’s 115 thru 124 Phase 1: Rm’s 126 thru 131, Rm’s 135 thru 146 Phase 2: Rm’s 159 thru 173 Phase 3: Rm’s 147 thru 155 Phase 4: Rm 101 and Rm’s 110 thru 114 Restrooms 133, 134, 174 and 175 Hallways 125, 132, 157, 158, 181 and 182 |
|
07/15/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | rooms 114 through 124, rooms 126 through 131, area 137, rooms 136, 148, 157, rooms 159 through 165, rooms 167 through 171, rooms 151 through 157, 158, rooms 110 through 114. Rooms 132 through 152 and rooms 133, 134, 154, 155. OK to install ceiling tile. | |
07/02/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | restrooms 133 and 134 OK | |
06/28/2019 | ELECTRIC - ABOVE CEILING | Partial Approval | room 101, restrooms 106 and 107, reception 116 hard soffit ok. |