Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/17/2019 | MECHANICAL - FINAL | Approved | OUTSTANDING ISSUES COMPLETED | |
| 07/11/2019 | MECHANICAL - FINAL | Partial Approval | REVIEW OF AIR BALANCE REPORT COMPLETED | |
| 07/08/2019 | MECHANICAL - FINAL | Partial Approval | Contractor to send photos of ADA water closet installation and Cove base in bathrooms Pending chlorination report and balance report to Bob Sherry an office Pending engineering and fire finals Pending 2035 approval |
|
| 07/05/2019 | MECHANICAL - FINAL | Not ready for Inspection | Restrooms are not complete. Raw lumber being used on the roof. Hood did not pass smoke containment test. Hood fan missing grease receptor. Stopped inspection. | |
| 07/02/2019 | MECHANICAL - FINAL | Not ready for Inspection | 1- Work is incomplete | |
| 06/27/2019 | MECHANICAL - FINAL | Not ready for Inspection | ||
| 06/13/2019 | MECHANICAL - FINAL | Partial Approval | Smoke test to 4’ grease duct only ok to double wrap |