Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/09/2019 | PLUMBING - ROUGH, SOIL | Approved | ||
| 06/21/2019 | PLUMBING - ROUGH, SOIL | Partial Approval | Plumbing rough and waste a long building to within 12 feet of HCS connection OK.? | |
| 06/18/2019 | PLUMBING - ROUGH, SOIL | Correction Required | No plumbing or electrical ca run parallel in the footing. Install Cleanouts as discussed. Tracer wire required on plumbing outside the building footprint. There may be other corrections upon inspection of corrections. |
|
| 06/13/2019 | PLUMBING - ROUGH, SOIL | Denied | Rebar to be number four or better, provide clearance from earth to rebar, complete installation of straps at footer, DWV to have 5 foot head pressure, plastic pipe not to be on air test. This Inspection is not complete at this time. |