Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T19CM01102
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/17/2020 | ENGINEERING - FINAL | Approved | Approved | |
| 06/22/2020 | ENGINEERING - FINAL | Partial Approval | Partially approved. Waiting for completion of landscaped areas | |
| 06/19/2020 | ENGINEERING - FINAL | Partial Approval | Partially approved OK for TCO. Waiting for completion of development package permit. | |
| 06/18/2020 | ENGINEERING - FINAL | Partial Approval | Partially approved. OK for TCO. Shannon with bespoke builders. Remove all stormwater controls and construction debris, also dirt piles and fill in the hole. Remove temporary dumpster. Remove dirt blocking basin inlet and reinstall existing riprap. Stabilize all bare dirt areas disturbed during construction for completion of development package permit Required for final approval as combination permit. | |
| 06/05/2020 | ENGINEERING - FINAL | Partial Approval | Partially approved. Schedule required inspections from development package permit. Chris 909-4628 |