Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 07/31/2019 |
BUILDING - PROGRESS |
|
Approved |
|
| 06/18/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Top out OK to pour, revision required at CMU control joint above rollup door in order to complete. |
| 06/14/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Top out OK except at rollup lentil. |
| 06/13/2019 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Cancel per Contractor |
| 06/12/2019 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Work incomplete at this time. |
| 06/10/2019 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Canceled by contractor |
| 06/07/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Third lift. |
| 06/04/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Second lift OK. |
| 06/03/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
First lift OK at louver, OK to proceed |
| 05/31/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
First Lyft CMU wall OK, provide documentation on reinforcement at louver. |