Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
Permit Number - T19CM01021
Inspection Description - MECHANICAL - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/03/2020 | MECHANICAL - INTERMEDIATE | Approved | Approved | |
| 11/03/2020 | MECHANICAL - INTERMEDIATE | Approved | Approved | |
| 07/16/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Roof Level; 2 single restrooms. Ok to cover walls and ceiling. | |
| 07/10/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Roof top bar area and restrooms. | |
| 07/07/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Elevator lobby area ceilings at Level #7 through Level #14. | |
| 06/17/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Mechanical in ceilings and walls in rooms 1004, 1104; 1204; 1304; 1404. | |
| 06/10/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Level #14; Unit Rooms #1400-1420. Grease duct smoke test of 18” duct system from kitchen hood to end of back of the house corridor. | |
| 06/05/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Information only, scheduled smoke testing for grease duct system (20”). | |
| 05/15/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Level #1; Kitchen area and break room. Ok to sheetrock walls in progress areas. Hydronic lines on Levels #13 & 14. Ok to cover shaft walls. | |
| 05/12/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Level #13; Unit Rooms #1300-1320. Duct system in place. | |
| 05/11/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Level #12; Unit Rooms #1200-1220 | |
| 05/06/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Hydronic Piping at Levels 9-11 | |
| 05/01/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | RVI Partial. (VRI). Inspections performed on 30 April. | |
| 04/30/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | Partial. Level #11; Unit Rooms #1100-1120. | |
| 04/28/2020 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | Not ready. Contractor cancelled | |
| 04/22/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | RVI Level #10; Unit Rooms #1000-1017 | |
| 04/17/2020 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | RVI | |
| 04/13/2020 | MECHANICAL - INTERMEDIATE | Partial Approval | RVI Level #8; unit rooms #800-820. Ok to insulate and cover walls. | |
| 04/09/2020 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | Not ready. Unable to contact superintendent to set up for video inspection. Called at 1:23 and 3:009. |