Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 11/03/2020 |
ELECTRIC - FINAL |
|
Approved |
Approved |
| 10/06/2020 |
ELECTRIC - FINAL |
|
Approved |
|
| 09/30/2020 |
ELECTRIC - FINAL |
|
Partial Approval |
Partial. Room Units on Levels 11; 12; 13. |
| 09/23/2020 |
ELECTRIC - FINAL |
|
Partial Approval |
Partial. Level #7 & 8 Electric rooms. Ensure all wall and ceiling penetrations are properly patched and fire caulked. |
| 09/22/2020 |
ELECTRIC - FINAL |
|
Partial Approval |
Partial. Level #9 and Level #10 Electric rooms. Equipment to be energized at a later date. |
| 09/17/2020 |
ELECTRIC - FINAL |
|
Denied |
Denied. No contact information no message |
| 09/14/2020 |
ELECTRIC - FINAL |
|
Denied |
Denied. Electric room at Level #10; unable to inspect due to trash condition of room. |
| 09/10/2020 |
ELECTRIC - FINAL |
|
Partial Approval |
Partial. Level #11 electric room, ensure all penetrations are properly caulked. Need protection for MC Cable running through slab. |
| 09/04/2020 |
ELECTRIC - FINAL |
|
Partial Approval |
Partial. Electric rooms at Levels #12; 13; 14. Ensure all penetrations are properly fire caulked. |
| 09/01/2020 |
ELECTRIC - FINAL |
|
Not ready for Inspection |
Not ready. Contractor cancelled. Will reschedule for 2 September. |
| 08/25/2020 |
ELECTRIC - FINAL |
|
Partial Approval |
Partial. Level #13; Room Units #1300-1321. Level #14; Room Units #1400-1420. |