Inspection Status: Approved
Inspection History: SHEET ROCK NAILING
| Date |
Description |
Inspector |
Results |
Comments |
| 11/03/2020 |
SHEET ROCK NAILING |
|
Approved |
Approved |
| 11/03/2020 |
SHEET ROCK NAILING |
|
Approved |
Approved |
| 06/25/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial, Unit Rooms #1400-1420. Ok to tape progress areas. |
| 06/17/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #13; Room Units #1300-1320. Ok to tape progress areas. |
| 06/02/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #12 corridor ceilings. Ok to tape progress areas. |
| 06/01/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #1; all areas except for conference rooms; restrooms; and kitchen area. Ok to tape progress areas. |
| 05/28/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Levels #10 & 11; Unit Rooms and corridors. Ok to tape progress areas. |
| 05/27/2020 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
|
| 05/11/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #9; Unit Rooms #900-920. Ok to tape progress areas. |
| 04/28/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #8; Unit Rooms 802; 805; 807; 808; 809; 810; 811; 812; 814; 815; 816; 817; 818; 819. Lobby areas. Ok to tape progress areas. |
| 04/21/2020 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
Contractor cancelled, rescheduled for 22 April. |
| 04/20/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Lobby entry area first layer of sheetrock in place. Ok to hang second layer to complete 2 hour rated assembly. |
| 04/17/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
RVI Level #8; Rooms #806 through 820. Ok to tape progress areas. |
| 04/15/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
RVI Level #7; unit Rooms #700-717 ( except for rooms 704 and 705). Ok to tape progress areas. |
| 03/16/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Level #7; Rooms and corridors. Level #8; Rooms and corridors. Level #9; corridors only. Ok to tape progress areas. |
| 02/28/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Level #7, sheetrock top out at 18" below deck above. Ok to to hang second layer in progress areas. |
| 02/25/2020 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
Contractor cancelled, will reschedule for 26 February. |