| 04/09/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
North side 3rd lift |
| 03/22/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK to grout second lift on north and east wall |
| 03/20/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
RETAINING PORTION OF WALL OK TO GROUT (4') |
| 03/12/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
first lift ok to grout, keep photos of verticals meeting the required lap, as the verticals from 1st to 2nd lift are not on site, nor in the cells. |