Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/08/2019 |
ELECTRIC - INTERMEDIATE |
|
Approved |
|
| 10/04/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
ECO OK to Clear, OK to energize CT can from transformer, Panels to be locked, site superintendent and electrical contractor only to have keys. |
| 09/05/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
All OK except at walk-in refrigeration area. |
| 09/03/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
OK pony walls at Döner processing. |
| 08/23/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
all Electrical in walls from Grid Line A to E ok. |