Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2019 | PLUMBING - INTERMEDIATE | Approved | secure closet flanges with tap cons or other concrete approved screws not with grout. | |
| 02/14/2019 | PLUMBING - INTERMEDIATE | Partial Approval | Nail protect dryer vent Secure four gang box entry Provide for future solar and water heater Secure exterior hose bib’s Secure closet flanges Nail protect condensate line |
|
| 02/12/2019 | PLUMBING - INTERMEDIATE | Partial Approval | DWV OK, NEED PEX AND MAIN WATER LINE TEST. 3040- PARTIAL, LINE AND TRACER OK, NEED TEST |
|
| 02/07/2019 | PLUMBING - INTERMEDIATE | Not ready for Inspection | grout under tub. Rough in TNP piping. Need ABS piping and pex under water test at time of inspection |