Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
Permit Number - T19BU00495
Inspection Description - BUILDING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/10/2020 | BUILDING - FINAL | Approved | ||
02/07/2020 | BUILDING - FINAL | Continued | Meeting at site with engineers and Lance. Review poor work performed by contractor. Instructed what needs to be corrected inorder to sign off on project. Discussed the use of #57 rock in area of a walkway and the poor condition of fill/grade at building foot print. Contractor said they were not done but the equipment was parked ready for pickup and daughter said they were done. Stayed to watch the contractor grade site and apperas complete but poor workmenship. |
|
02/05/2020 | BUILDING - FINAL | Continued | Phone call from B & C Contracting about poor work at 4018 E Grant Rd. Refuses to correct poor workmenship. Permit T19BU00495. Meeting with Lance and contractor set up for Friday 02/07/20, 10am. | |
02/04/2020 | BUILDING - FINAL | Continued | Slab concrete removed. All debri removed from site. Area of building slab left in a sunken/depressed condition. with gravel looely spreed accross area. Fill is needed to make area level and flush with rest of site. Area where curbs were removed along Grant Rd were left depressed and some gravel was dumped without spreeding/grading. This is a tripping hazzard and some dirt was left in the street. Talked with contractor (Jessie) at end of day, told her this is unacceptable and needs to be corrected. Also told her to go to site and see why I can not accept this work. She said this is not my job, that I am only there for safety during demo and she will call Dave Koss. |
|
02/03/2020 | BUILDING - FINAL | Continued | Slab being removed. | |
01/31/2020 | BUILDING - FINAL | Continued | Debri removed. Pulling up slab. | |
01/28/2020 | BUILDING - FINAL | Continued | Visited site and waited for TFD to arrive. They will practice braking in at the steel doors prior to contractor starting the demolishing of the building. | |
01/28/2020 | BUILDING - FINAL | Continued | Contractor had taken down the east wall and dropped 1/4 of the wood roof structure and removed the "HOUSE OF CARPET" neon sign but slightly damaged it and cut it into 3 pieces and set aside. Equipmentproblems with their bobcat and did not start up again after about 1.5 hours. Finally moved the sign into the city owned building just west of the location and locked up the building. After work resumed they spent the majority of time in salvaging the wood joists in the roof structure. All walls(masonry) were down by 4:45. | |
01/27/2020 | BUILDING - FINAL | Continued | Contractor called - will start 1/28/20 Inspected T19BU00495 - Excavator on site. |
|
01/16/2020 | BUILDING - FINAL | Continued | Asbestos abatement appears completed. Building secure | |
01/13/2020 | BUILDING - FINAL | Continued | Asbestos not completed but contractor not on site when inspector arrived and found back door not closed and locked.Contractor arrived shortly thereafter and was unaware that door was not closed and locked. Notified downtown and the demo contractor. | |
01/10/2020 | BUILDING - FINAL | Continued | Demo site. Abestos abatement proceeding. | |
01/07/2020 | BUILDING - FINAL | Continued | Asbestos abatement on going. | |
01/06/2020 | BUILDING - FINAL | Continued | Demolition location on Grant Rd. Asbestos abatement in progress. Floresent light tubes left in a barrel outside in back of building. |