Inspection Status: Re-inspection required
Inspection History: COT - SIGN - Sign Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/07/2019 |
COT - SIGN - Sign Final |
CTREVI |
Prior to Intermediates |
Entered by CTREVIL1 - 1. The north horizontal offset beam remained rigidly affixed to the north vertical supporting I-beam while the four (4) 1 ¼-inch diameter A325 bolts attaching the two parts were replaced one at a time.
2. The four (4) 1 ¼-inch A325 bolts attaching the north vertical tapered upright to the north horizontal offset beam were removed, a replacement vertical tapered upright was placed on the same location on the horizontal offset beam, and four (4) new 1 ¼-inch diameter A325 bolts were installed in place of those removed.
3. The south vertical tapered upright remained rigidly affixed to the south horizontal offset beam while the four (4) 1 ¼-inch diameter A325 bolts attaching the two parts were replaced one at a time.
4. The south horizontal offset beam remained rigidly affixed to the south vertical supporting I-beam while the four (4) 1 ¼-inch diameter A325 bolts attaching the two parts were replaced one at a time. |