Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 03/14/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work is completed and confirmed by Natasha Lemay from KEG. Last bit of work was concrete bench in the manhole.No issues |
| 02/28/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
pipe linned on 2/1/19 no issues or other repairs needed |
| 01/29/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
new manhole on ochoa with a 10x10 asphalt patch. No issues |
| 12/20/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor onsite paving and should be cleaned up by tomorrow - CN |
| 12/19/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor onsite back filling MH and will be paving tomorrow - informed him to make sure patch work was level and to spec - CN |
| 12/18/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
they started excavation work today - they damaged some asphalt with equipment that will have to be fixed - CN |
| 12/17/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet for pre-con - discussed work to be done and that they are will be starting tomorrow - CN |